    I purchased a OTP 3 years ago and the final sunset date is coming up in 7Months, the original sunset date was October this year but developer has extended the sunset for another 4 months due to an extension clause, as for the development, they are currently still digging a hole( its deep ) but no foundation has been layed out yet. The apartment is 10 storey with 3 basement parking.
    I've been told its is highly unlikely the development will be finished in 7 months, I've spoken with my lawyer and they have advised me to wait out till sunset clause date. I'm feeling very anxious as what to do and what to expect should i seek opinion from another lawyer or should i just wait it out? has this happened to you?
    I don't understand why they are seeking to extend the sunset date if the development wont be going ahead.

    Appreciate your feedback.
     
  2. Trainee

    Trainee Well-Known Member

    Joined:
    24th May, 2017
    Posts:
    10,327
    Location:
    Australia
    Maybe theyre looking to sell the project. Triggering the sunset clause would mean they have to return deposits.
     
    Shahin_Afarin likes this.
  3. Tnoz

    Tnoz Member

    Joined:
    29th Jan, 2019
    Posts:
    11
    Location:
    Rockdale
    The project wont be developed in time even if it was to be resold. I don't understand why holding out longer would help with reselling the project?
     
  4. Trainee

    Trainee Well-Known Member

    Joined:
    24th May, 2017
    Posts:
    10,327
    Location:
    Australia
    So whats the problem then? Youve waited this long. A few more months.

    Maybe the rate cuts will make it easier to sell the project.
     
  5. JDM

    JDM Well-Known Member

    Joined:
    19th Jan, 2016
    Posts:
    465
    Location:
    Brisbane
    Does the developer have a right to extend the sunset date further? If so, waiting might not be the best strategy. Otherwise, I agree with that approach.

    Not sure where the property is located. There’s an argument a sunset date can’t be extended if it’s Qld.
     
  6. Shahin_Afarin

    Shahin_Afarin Residential and Commercial Broker Business Member

    Joined:
    18th Jun, 2015
    Posts:
    1,658
    Location:
    Sydney
    Completion will take 12-18 months. There may be an issue with finance thats stopping them from commencing construction.

    How many units have they sold within the complex and when did they commence excavation?

    Do you feel comfortable with the project (even if it was built in 7 months time) in light of the recent events @ Opal and Mascot?
     
  7. Trainee

    Trainee Well-Known Member

    Joined:
    24th May, 2017
    Posts:
    10,327
    Location:
    Australia
    You have to realise the buyers are not the priority to the developer.
     
  8. Trevor Skinner

    Trevor Skinner Member

    Joined:
    12th May, 2016
    Posts:
    12
    Location:
    Melbourne
    Your solicitor is correct. Most Off the Plan contracts allow for a purchaser to withdraw from the contract once the sunset date is reached. No compensation is paid, you will get your deposit back and if it was invested any interest it gained, these are they most common terms.
     
  9. fobo

    fobo Well-Known Member

    Joined:
    17th Mar, 2017
    Posts:
    101
    Location:
    Sydney
    I’ve been waiting 3 years for something similar. Developer went broke, new owner now. I think they’re going to pull it off in time, they went from an empty block to almost lockup in less than 10 months

    Was advised the same thing, just have to wait
     
  10. Tnoz

    Tnoz Member

    Joined:
    29th Jan, 2019
    Posts:
    11
    Location:
    Rockdale
    Hi Fobo,

    That's really quick for a development, can i ask how big this project is?

    eg how many floor levels, basement levels? is the 10month from the moment the hole was already dug?

    Thanks
     
  11. fobo

    fobo Well-Known Member

    Joined:
    17th Mar, 2017
    Posts:
    101
    Location:
    Sydney
    Much smaller sorry, 8 townhouses all above ground. Started from an empty block
     

Price Accounting provide tax services and advice to developers on issues incl GST, Tax + Structure. Our free developer toolkit covers many of the key elements and is critical to a new development tax plan. Email for your copy and our new client pack.