How Long Does It Take to Build 12 Storey Apartment With 3 Level Basement

Discussion in 'Development' started by Tnoz, 25th Jul, 2019.

Join Australia's most dynamic and respected property investment community
Tags:
  1. Tnoz

    Tnoz Member

    Joined:
    29th Jan, 2019
    Posts:
    11
    Location:
    Rockdale
    Hi All,
    want to find what the approximate time frame it takes to build a 12 Storey Apartment with 3 level basement?
     
  2. JohnPropChat

    JohnPropChat Well-Known Member

    Joined:
    10th Sep, 2015
    Posts:
    2,293
    Location:
    Middle Earth
    how much money you got?

    Seriously though, do you have the building approvals sorted? Finance? Need pre-sales?

    Without knowing much information, I would say 3 years.
     
    Shazi likes this.
  3. Tnoz

    Tnoz Member

    Joined:
    29th Jan, 2019
    Posts:
    11
    Location:
    Rockdale
    sorry for the insufficient information, just want to understand how long it takes to build from the point there is a hole in the ground. I'm not a developer just interested in purchasing.
     
  4. Scott No Mates

    Scott No Mates Well-Known Member

    Joined:
    18th Jun, 2015
    Posts:
    27,248
    Location:
    Sydney or NSW or Australia
    Have they achieved the DA? Are they lodging a S96? Is it going to the L&E Court?

    Have you requested the construction programme/critical path?

    What's the construction methodology?

    Have the plans been reviewed for buildability?

    Is there an experienced Development Manager, PM, site manager, contracts manager, structures and fixout foreman?

    What stage is the construction finance? Does each progress payment require scrutiny of a QS?

    What's in the ground? (Sand, shale, clay, rock, sandstone, Play-Doh, loam etc? Have the foundation been reviewed by a geotechnical engineer & designed by a structural engineer?

    I'd punt 5 wks/floor on the structure, another 3-4 weeks/floor for the fixout, 3 months on excavation, extra for shoring, 4 weeks inclement weather.

    DA for strata subdivision, registration of titles etc can chew up another few months.

    Generally a lift takes 26 weeks which is the item with a longest lead time.
     
  5. Tnoz

    Tnoz Member

    Joined:
    29th Jan, 2019
    Posts:
    11
    Location:
    Rockdale
    Hi Scott No Mates,

    I know DA is approved, there's no foundation layed out yet, so far they've dug a deep hole.

    Do you think its possible to complete a 12 level apartment with 3 level basement in 7 months?
     
  6. Westminster

    Westminster Tigress at Tiger Developments Business Member

    Joined:
    3rd Jun, 2015
    Posts:
    11,356
    Location:
    Perth
    Absolutely definitely 100% not going to happen
    If you've purchased OTP and have a sunset clause start thinking about what you want to do
     
  7. Big Lez

    Big Lez Well-Known Member

    Joined:
    8th Mar, 2017
    Posts:
    75
    Location:
    Sydney
    I have worked on a few projects similar sized. Once they have finished excavation, I would estimate somewhere between 12-24 months.

    The thing that slows the whole process down, is the internal fitout as it’s quite difficult to get all the various trades in sequence. It’s pretty amazing how quickly they construct the all the slabs/outside shell of the building though.

    If the builder is a fairly long term established construction company, they typically use the same contractors on all their jobs and have the experience of all working in sync so they might be able to get it all built a lot quicker (around the 12-18 month mark).
     
  8. Big Lez

    Big Lez Well-Known Member

    Joined:
    8th Mar, 2017
    Posts:
    75
    Location:
    Sydney
    Definitely not.
     
  9. Scott No Mates

    Scott No Mates Well-Known Member

    Joined:
    18th Jun, 2015
    Posts:
    27,248
    Location:
    Sydney or NSW or Australia
    They have got substantial commencement, that's about how far it's going to go if there's only 7 months to go to the sunset date. The DA won't lapse now.
     