    " New " PPOR .

    Back of the house is sinking and needs stabilising . Roof needs replacing , bathroom , kitchen as well . Veranda roof leaks , need to replace Windows and split a couple of rooms ....

    Where do we start ???

    Triple garage is having the tandem bit split off to become a sound proofed recording studio complete with non parrallel wall to improve the acoustics !!!

    YES :cool::cool::cool:

    Cliff
     
    Bran likes this.
  2. chindonly

    chindonly Well-Known Member

    Joined:
    18th Jun, 2015
    Posts:
    336
    Location:
    Brisbane
    Musical man cave??
     
  3. See Change

    See Change Timing Lord Premium Member

    Joined:
    18th Jun, 2015
    Posts:
    2,146
    Location:
    Sydney
    Yep

    Cliff
     
  4. EN710

    EN710 Well-Known Member

    Joined:
    18th Jun, 2015
    Posts:
    2,162
    Location:
    NSW
    The man need to have his safe place before going around wrecking things (then fixing them) :rolleyes:
     
    ellejay and See Change like this.
  5. Propertunity

    Propertunity Exclusive Real Estate Buyers Agent Business Member

    Joined:
    19th Jun, 2015
    Posts:
    1,241
    Location:
    NSW
    In order of priority:
    Stop the house from sinking - underpin / stabilise
    Stop the water from coming in - fix the roof
    Get it watertight - replace the windows
    Do the rest as it suits you
     
    MTR, Ozzie in Texas and legallyblonde like this.
  6. THX

    THX Well-Known Member

    Joined:
    24th Jul, 2015
    Posts:
    869
    Location:
    Sydney
    Knock it down? build new?
     
  7. Xenia

    Xenia Adelaide Property Manager Business Member

    Joined:
    21st Jun, 2015
    Posts:
    2,347
    Location:
    4/136 The Parade Norwood, South Australia
    Underpin the house first.
    Roof second Including verandah roof.
     
    MTR and Ozzie in Texas like this.
  8. See Change

    See Change Timing Lord Premium Member

    Joined:
    18th Jun, 2015
    Posts:
    2,146
    Location:
    Sydney
    Proportunity

    Luckily the part of the house where the studio is , is a new extension and is built like a brick Sh..t house .

    Next job will be stabilising old part of house , ( need to do more research but current plan will be a drainage trench dug behind the house to stabilise water flow to start with , then foundation work , but will get consultants in etc ) designing new plan and starting from roof down .

    But still , studio comes first

    Knock down would be more expensive . 6-800 k plus . If we did that we'd have to build a big house other wise it would be undercapitalising the site and we don't want that . Current house is about the right size for us .

    For a couple of hundred , we can dramatically improve current house and improve value.

    We can also stagger the work in steps which will work well .

    Cliff