Hi, I am looking to build a duplex in Sydney and keen to get everyone's feedback on the below quote I got from a custom builder. Few things to note about the duplex - 5 bedroom, 3 bathroom, - Total land 700m2 so 350m2 per duplex - Internal area maximised per council regulation - Builder margin quoted 15% which i believe is quite standard around my area - Full design and engineering report to be completed and the below has been quoted based on DA approved plans which doesn't have exact measurements. - I have been advised to proceed with the design and CC application and engineer design totalling $12k to firm up the below quote. Sorry for the poor format. I am building this based on high end finish with the aim for selling one side and living in the other. Keen to get a view if anything stands out as ridiculous or understated? Description Quantity Rate Price Design and CC application 2.00 $ 3,500.00 $ 7,000.00 Long Service Levy 1.00 $ 3,500.00 $ 3,500.00 Insurance 1.00 $ 18,000.00 $ 18,000.00 Engineer design fees 2.00 $ 2,500.00 $ 5,000.00 Reece 1.00 $ 1,000.00 $ 1,000.00 Survey - Details 0.00 $ 900.00 $ - Survey - Set Up 2.00 $ 900.00 $ 1,800.00 Survey - Final 2.00 $ 900.00 $ 1,800.00 Preparations 2.00 $ 2,750.00 $ 5,500.00 Demolition 1.00 $ 22,000.00 $ 22,000.00 Remove Soil, Excavation 1.00 $ 21,000.00 $ 21,000.00 Concrete 291.00 $ 275.00 $ 80,025.00 Scaffold 2.00 $ 8,000.00 $ 16,000.00 Termite pertection 2.00 $ 1,480.00 $ 2,960.00 Frame Canpentery 2.00 $ 40,500.00 $ 81,000.00 Structure steel 2.00 $ 5,200.00 $ 10,400.00 color bond roof sheet 291.00 $ 95.00 $ 27,645.00 Engineer inspection fees 1.00 $ 1,500.00 $ 1,500.00 Façade finish 1.00 $ 8,500.00 $ 8,500.00 Brick materials 25500.00 $ 1.40 $ 35,700.00 Brick installation 25500.00 $ 1.45 $ 36,975.00 Brick cleaning 1.00 $ 2,000.00 $ 2,000.00 Cladding upstairs (hebel) 265.00 $ 135.00 $ 35,775.00 Window and Sliding Doors 2.00 $ 9,500.00 $ 19,000.00 Entrance Door & lock 2.00 $ 750.00 $ 1,500.00 Electrician 2.00 $ 12,500.00 $ 25,000.00 Plumber 2.00 $ 19,000.00 $ 38,000.00 Storm water upgrade 2.00 $ 7,500.00 $ 15,000.00 Air-con 2.00 $ 7,500.00 $ 15,000.00 Insulation 850.00 $ 7.00 $ 5,950.00 Plasterboard 2350.00 $ 15.00 $ 35,250.00 Water Proof 10.00 $ 600.00 $ 6,000.00 Stairs 2.00 $ 3,000.00 $ 6,000.00 Painting 2.00 $ 13,000.00 $ 26,000.00 Tiler allowed $35 per/m 465.00 $ 85.00 $ 39,525.00 Timber floor allowed $75 per/m 165.00 $ 115.00 $ 18,975.00 Shower Screen 6.00 $ 750.00 $ 4,500.00 Kitchen 2.00 $ 15,000.00 $ 30,000.00 pantry Joinery 2.00 $ 2,500.00 $ 5,000.00 laundry joinery 2.00 $ 2,000.00 $ 4,000.00 BBQ joinery 2.00 $ 3,500.00 $ 7,000.00 Timber Doors & Skirting 2.00 $ 5,000.00 $ 10,000.00 Fixer for timber work 20.00 $ 450.00 $ 9,000.00 Wardrobe, linen and WIR 16.00 $ 800.00 $ 12,800.00 Water Tanks & Pumps 2.00 $ 1,800.00 $ 3,600.00 Hot Water Heater gas 2.00 $ 750.00 $ 1,500.00 Kitchen Appliances 2.00 $ 2,500.00 $ 5,000.00 Driveway 2.00 $ 12,000.00 $ 24,000.00 Garage door 2.00 $ 2,500.00 $ 5,000.00 Glass handrail 2.00 $ 3,500.00 $ 7,000.00 Lanscaping 2.00 $ 8,000.00 $ 16,000.00 Building materials supply 2.00 $ 1,500.00 $ 3,000.00 Lightings 2.00 $ 500.00 $ 1,000.00 Bathroom PC items 2.00 $ 5,000.00 $ 10,000.00 Bin 1.00 $ 6,400.00 $ 6,400.00 Cleaning 2.00 $ 800.00 $ 1,600.00 Onsite cost Foreman 28.00 $ 1,500.00 $ 42,000.00 Labour 14.00 $ 1,000.00 $ 14,000.00 Builders Margin $ 118,287.00 GST $ 101,696.70 Total Balannce $ 1,118,663.70
I can't speak to each line item but based on the total and the size you are assuming it will cost around $1600 per sqm which I don't believe would get you high end finishes in Sydney but your idea of high end and mine may differ 2 line items seem a bit skinny 1. lighting - I assume this is feature lights and all downlights and exterior lights. I can spend $500 just on my island bench light so this needs to be increased a lot 2. bathroom PC items - I'm assuming this is toilets, baths, tapware and as each house has 3 bathrooms the $5000 is not going to go far