Hi, I think type of contruction (I.e brick, cladding, brick veneer, double brick, concrete slab, bearers and joists etc) and site constraints...
Assuming all roofs discussed here are basic colorbond: The facade design you have shown is a flat roof/parapet/box gutter design. Generally most...
Hi, 2 metres of slope over what distance? Slab should be designed by a structural engineer in accordance with AS2870 so I'm not sure what the...
This would be the process from a town planner and builder's perspective: 1. Purchase (Due diligence) - Planning affectations (Bushfire, flooding,...
As @sammy26 has mentioned, this is an error in the code. Our planning team has confirmed this with the DPIE grapevine and have been advised it's...
www.rg-homes.com.au is a bespoke residential home builder servicing Metro Sydney specialising in the following builds: Custom New Homes Dual...
You can nominate another person to act as the role of a PCA, it doesn't necessarily need be the entity that issued the PCA. You can also change...
Whether you’re buying an established business associated with property (lease or sale) or buying/leasing property to start or house a business or...
Hi, you can request a variation to the 4m development control, make sure the objectives of the control are addressed. There's no guarantee that...
Who's accountable for the OC would be a legal question dependant on the contract. It seems Odd the builder would manage the CC and inspections...
If the secondary dwelling doesn't have approval, and you want to make it legit, you'll need a building certificate for any unauthorised works and...
Hi Fred, Do you want to: 1. Subdivide the land? 2. Build a dual occupancy 3. Or building a dual occupancy and subdivide the land? For now your...
Hi Forsty, Home builders usually have a process where you pay a deposit (Say $1000-$2000) for an initial feasibility/siting. They will order a...
Hi mate, Austral/Leppington, Box Hill and North Kellyville are very different to Gordon. Gordon is an established suburb with existing houses....
Informal access to information searches via Council generally take between 2-14 days and the timeframe really depends the particular Council. We...
Hi Josh, It’s too hard to say because it depends on the existing situation. Sewerage, water, gas and electricity you can get away with more or...
Went for the duck egg blue cliche for the hamptons style kitchen lol [ATTACH]
If you have the space, you won't regret it. I had to rip out all old electrical and plumbing and rough in new services down lower, the additional...
First step would be to find out if the apartments actually have consent and if a construction certificate and occupation certificate was issued....